Installation of a fifth and sixth generating unit at Mica dam has taken eight years.

Dam expansion done as BC Hydro demand slumps

Four per cent rate increase expected next year to keep up with big maintenance, construction of Site C on the Peace River

BC Hydro has completed one of its mega-projects, expansion of the Mica Dam on the Columbia River to full capacity, as the utility weathers a slump in mining and continued delays in liquefied natural gas projects.

The addition of two water turbines to Mica cost $714 million, plus a new high-voltage transmission line to carry power to the Lower Mainland and Vancouver Island. BC Hydro has also moved up plans to add a sixth turbine at the Revelstoke Dam, as work continues on the Site C project on the Peace River.

[A look inside the Mica Dam project here]

With major upgrades at the Ruskin Dam in the Fraser Valley and the John Hart Dam on Vancouver Island also underway, BC Hydro has applied for a four per cent rate increase to take effect on April 1, 2017. That follows increases of nine and six per cent in the past two years, mainly to finance major projects and pay down debt.

The four per cent rate is a one-year interim application to the B.C. Utilities Commission, which would add about $4 a month to the average residential electricity bill. Faced with mine shutdowns and uncertainty in large LNG projects, BC Hydro put off its three-year rate proposal when it filed the application in February.

Under a 10-year rate plan imposed by the B.C. government, rates are to increase 3.5 per cent in 2018 and three per cent in 2019. After that, authority over rate setting is to return to the BCUC.

Despite the current downturn for industrial customers, BC Hydro projects demand to increase 40 per cent over the next 20 years, due to population and industrial growth.

It has also scheduled major maintenance at Mica, with two original turbines built in the 1970s due to come out of service for 18 months each.

The B.C. government has proposed to Ottawa that a second power grid link to Alberta be built to help that province retire its coal-fired power plants.

 

Just Posted

River Monsters attract nearly 300 swimmers to their two-day meet

This was the third year for the now-annual event

PHOTOS: Sasquatch Days about ‘being proud of being Sts’ailes’

The joint event between Harrison and Sts’ailes returned to the village for its eighth year

‘This was my baby’: Music teacher to retire after 29 years at Kent Elementary

Brenda Di Rezze will be saying goodbye to her music room at the end of this school year

New Farmer’s Market coming to downtown Hope

Markets will be hosted every Friday on 3rd Avenue

SD78 growth plan to focus on inclusive learning, reading

Data collection and collaboration will help schools meet goals, superintendent says

10 facts about Father’s Day

Did you know that the special day for dads was first celebrated in 1910?

Parents of BC murder victim want personal belongings returned

Lisa Dudley’s parents, Rosemarie and Mark Surakka, were at the Mission RCMP detachment Sunday

B.C. VIEWS: When farmland protection doesn’t protect farmers

Secondary residences aren’t mansions, families tell Lana Popham

Bombers down B.C. Lions 33-23 in season opener

Former Lion Andrew Harris leads Winnipeg with 148 rushing yards

Northern B.C. family remembers murdered Indigenous woman with memorial walk

Still no closure for Ramona Wilson’s family 25 years later

Pride flag taken down by Township of Langley

Woman said she was told it was removed from her front yard because of a complaint

B.C. university to offer mentorship program for former youth in care

Students using the provincial tuition waiver program will soon be able to form a community at KPU

Cyclists competing in one of the toughest bike races on the planet pass through Fernie

Divide riders looking strong as they finish first leg of 4160 km race

You might not know these B.C. records are public

Hired a lawyer to file a civil claim? Those are published online

Most Read