Construction of the 19 km Spuzzum section of the Interior-Lower Mainland transmission line

Merritt-Coquitlam power line completed

A year behind schedule and over-budget, high-voltage line subject to arbitration between BC Hydro and its contractor

A year behind schedule and $18 million over budget, the latest high-voltage line of the BC Hydro grid has been completed from Merritt to Coquitlam.

The new line parallels the existing main line supplying the Lower Mainland and Vancouver Island from hydro dams on the Peace and Columbia Rivers. It was originally to be completed in 2014, but the main contractor fell behind and BC Hydro used its own crews to complete one of the most difficult portions, a 19 km stretch north of Hope.

The final cost for the 247 km line is expected to be $743 million, which Energy Minister Bill Bennett said is about two per cent more than the initial $725 million budget.

“There is an ongoing arbitration between BC Hydro and [contractor] Flatiron Graham as to who’s going to bear the cost of the delay, because the project was delayed by a year,” Bennett said in an interview Friday.

It’s the first 500-kilovolt line added to the BC Hydro grid in 40 years, to keep up with demand from a growing southwestern B.C. population and increase reliability in the event of disasters.

“You always have the potential for a big avalanche or a mudslide, even an earthquake, to take out one or two of your big transmission lines, bringing electricity in from the two rivers, the Columbia and the Peace,” Bennett said.

NDP energy critic Adrian Dix said the project started out with a $600 million estimate, making it $143 million over budget. He said it’s the latest in a series of cost overruns, including the Northwest Transmission Line north of Terrace, the Dawson Creek-Chetwynd line and the Iskut extension in the northwest.

Bennett said BC Hydro is under-budget on its overall capital construction plan, including $100 million under budget on reconstruction of five generating units at the W.A.C. Bennett Dam on the Peace River, and there is no additional effect on rates.

BC Hydro is committed to a capital budget of $2.4 billion a year for the next 10 years, including construction of the Site C dam on the Peace River and reconstruction of the Ruskin Dam in the Fraser Valley and the John Hart Dam on Vancouver Island.

 

Just Posted

Volunteers risk their lives to save others

SAR training prepares them for the job

Many moving parts to economic development

Tourism is only part of the answer

Window art a sign of the season

B.C. artist paints windows across the province

Get all your stocking stuffers, and the stockings, too

Beta Sigma Phi Christmas Craft Sale returns

VIDEO: Fraser Valley Bald Eagle Festival

This year’s event featured six stops, including viewing points and activity centres.

Methadone treatment not as effective for mentally ill, homeless: study

SFU study suggests unstable housing makes it hard to stick to treatment regimen

Wet weather expected for much of coastal B.C.

The Weather Network is calling for up to 200mm of rain to fall in some areas of the South Coast and Vancouver Island

B.C. reporter reflects on covering Charles Manson

Charles Manson, leader of a murderous cult, died on Sunday at 83

Port Mann, Golden Ears traffic up since tolls removed: report

City staff report says congestion woes easing on Pattullo Bridge as a result

Convicted child sex offender’s sixth lawyer resigns before sentencing

One time school board candidate Corey Neyrinck case delayed in BC Supreme Court yet again

ICBC overbilling for crash repairs not the problem, dealers say

Collision repair shops reject union claim of inflated costs

TransLink mulls distance-based fares, low-income discounts

Metro Vancouver transit agency launches final phase of fare review

B.C. groups to address child sex abuse in sports

viaSport is organizing a full day of education in association with Canadian Centre for Child Protection and the Coaching Association of Canada.

Most Read