Undersea cable pitched for clean energy

A company known mostly for wind projects is reviving a proposal to connect the Vancouver Island and Washington electricity grids

Wind farm development in northeastern B.C. Proponents of a new power line between Vancouver Island and Washington say it would make wind power a more stable source.

VICTORIA – With BC Hydro struggling to control electricity rate increases and cutting back on private power acquisition, a company known mostly for wind projects is reviving a proposal to connect the Vancouver Island and Washington electricity grids.

Sea Breeze Power Corp. wants to build a 50 km transmission cable under the Strait of Juan de Fuca to connect substations near Port Angeles and Victoria. To finance the project, it’s looking for a 10-year deal to assemble surplus U.S. power and sell it to BC Hydro at a flat rate of $69 per megawatt hour.

Sea Breeze CEO Paul Manson said the power purchase would finance the construction of the cable and deliver a steady source of electricity to B.C. at lower cost than new sources built in the province. It would also improve power quality and reliability for Vancouver Island residents, he said.

First proposed in 2006, the project has received environmental permits from both sides of the border. It was rejected by the B.C. Utilities Commission, which approved upgrading the existing power line from the B.C. mainland to Vancouver Island instead.

Sea Breeze developed a wind project at Cape Scott on northern Vancouver Island, and has plans and permits for other wind sites on the B.C. coast and the Peace River region. Manson said the Juan de Fuca cable would stabilize wind power supply on the B.C. coast, where wind speeds peak in winter, with inland Washington sites where it’s windiest in summer.

Manson said U.S. policy led to major wind development that leaves the the Pacific Northwest with an excess of power in spring, meaning the Washington power utility has paid BC Hydro to take its excess when hydro dams are full.

The cable would also give B.C. more capacity to buy cheap overnight coal and nuclear power from the U.S., which BC Hydro already does with its main connecting line along Interstate 5, he said.

Energy Minister Bill Bennett said the Juan de Fuca cable is one of many proposals that came forward as BC Hydro developed its integrated resource plan. That plan estimates that with conservation and efficiency improvements in B.C., the province will need more electricity supplies within eight years.

The company has not yet demonstrated that it can assemble the firm electricity it proposes to sell, and the project has “a pretty steep slope to climb,” Bennett said.

 

Just Posted

Risk of ‘deadly avalanches’ leads to warning for B.C.’s south coast

Weak layer of snow on Vancouver Island, Lower Mainland could trigger an avalanche

Another snowfall warning for Lower Mainland

Another 5-10 cm expected for Metro Vancouver, Fraser Valley and Sunshine Coast

Saskia and Darrel kick off spring tour with Chilliwack concert

Stories of the Great Plains delivered in Gaelic, French and more

Harrison to participate in inter-municipal business licence program

Construction companies and related businesses will be able to work across the Fraser Valley in 2020

RCMP officer reaching out to youth about intimate partner violence

Chilliwack officer and friends of Maple Batalia team up to encourage bystanders to speak up

Sell regulated heroin to curb B.C.’s overdose problem: report

B.C. Centre on Substance Use points to organized crime and money-laundering as contributing factors

Galchenyuk scores in OT as Coyotes edge Canucks 3-2

Vancouver manages single point as NHL playoff chase continues

B.C. legislature moving suspended staff controversy to outside review

Whale watching, Seattle Mariners trips billed as emergency preparedness, Speaker Darryl Plecas says

Two boys saved after falling through ice in Coquitlam

RCMP say a Good Samaritan pulled the kids to safety

More people signing up for compulsory vaccines

Maple Ridge mom says public tired of hearing about measles

UPDATE: Man charged in stabbing of woman, off-duty cop outside B.C. elementary school

Manoj George, 49, is facing two counts of aggravated assault and two counts of assault with a weapon after the incident on Wednesday, Feb. 20.

Why do zebras have stripes? Perhaps to dazzle away flies

Researchers from University of Bristol look into why zebras have stripes

Poll: More voters believe Canada doing worse under Trudeau government

22 per cent believed the country is doing better and 27 per cent said things are the same

HBC shuttering Home Outfitters across Canada

North America’s oldest retailer is revamping its various stores to improve profitability

Most Read