Agassiz-Rosedale Bridge construction could start in 2021, MLA says

The project is expected to cost substantially more than budgeted in 2017

The Agassiz-Rosedale Bridge could be under construction as soon as spring 2021, although according to Chilliwack-Kent MLA Laurie Throness, there’s still a lot that needs to be done before that can happen.

On Wednesday, June 12, Throness met with the Ministry of Transportation’s district manager (Lower Mainland District) Elena Farmer to discuss the status of the Agassiz-Rosedale Bridge seismic upgrades.

The engineering design process for the bridge has just begun, he said, and is expected to be finished by the end of the year. After that, the project will need to go through tenders, permits and consultation before construction can take place.

“They probably won’t start the work right during the winter, so it will probably be spring 2021 when the work actually happens,” he said.

Importantly, he added, the cost of the bridge upgrades is expected to be “much more” than expected.

When the project was first announced in 2017, the projected budget was supposed to be $36 million for both the Agassiz-Rosedale Bridge and the Rosedale Overhead.

RELATED: Province commits $36 million to Rosedale and Agassiz-Rosedale bridge

According to Throness, the Rosedale Overhead cost more than expected, as did recent upgrades to Pier 7 on the bridge.

The pier was being scoured by the fast-moving river, and needed to be shored up to keep the bridge safe.

Crews drove piles around the bottom of the pier on the river side and then connected the pier to one the bridge’s land piers, an underground substructure that helps keep the bridge stable. Construction for that project began in February and was completed sometime in April.

RELATED: Short closures on Agassiz-Rosedale Bridge during pier upgrades

“They don’t think it’s going to be nearly adequate,” Throness said about the remaining funds from the original $36 million.

Because of the expected increase in cost — Throness didn’t know how much of an increase was anticipated — the project will likely need to return to the legislature for more funding. If all goes according to plan, Throness said, the Agassiz-Rosedale Bridge project will be included in the 2020 budget.

Although construction isn’t expected to start until 2021 or later, Throness still plans to meet with Ministry of Transportation staff to share his thoughts on what should happen with the bridge.

“I think it’s inevitable, safety has to be our first concern,” Throness said about the project. “It has to be done, and it’s an unfortunate thing, and it’s going to inconvenience people for, I would think at least a year, crossing the bridge.

“But it’s my commitment to constituents to really ascertain their will and receive their suggestions.”

Throness has already put in some suggestions of his own for the bridge. So far, he’s proposed opening the walkway under the bridge, currently used for maintenance, so that pedestrians and bicyclists can travel beneath the cars.

“I think that would be a real tourist draw and it would be much safer,” he said, adding that Farmer said she would take that idea back to the design team for the bridge.

He’s also advocating for better organization for commuters during construction, something he says was lacking during construction on the Rosedale Overhead.

“I really want to improve the way we manage this construction,” Throness said.

“I don’t want to have a light at the beginning of the bridge and a light at the end of the bridge,” he added. “I want the light to be moving along with the construction so you can just quickly pass by the construction zone and we can minimize the disruptions.”



grace.kennedy@ahobserver.com

Like us on Facebook and follow us on Twitter

Just Posted

Hang gliding video gives stunning view of Harrison and Fraser river confluence

Aerial view shows striking difference between two rivers as they meet

Young Chilliwack singer launches career with French classic

Deanne Ratzlaff performs as featured vocalist in La Vie en Rose in Chilliwack, London and Paris

The most h-i-l-a-r-i-o-u-s spelling bee you’ll ever see in Chilliwack

Secondary Characters Musical Theatre hits the stage with The 25th Annual Putnam County Spelling Bee

Psychics, drones being used to search for missing Chilliwack woman with dementia

Volunteers pulling out all the stop to try to find Grace Baranyk, 86

Serious police incident unfolding at Sts’ailes

Small reserve near Agassiz surrounded by police vehicles, helicopter, ERT

Feds lowered poverty line, reducing the number of seniors in need: documents

Liberals introduced a poverty line that was below the prior low-income cutoff

BCHL: Alberni Valley Bulldogs have been sold

Victoria company has purchased BCHL team, but will keep it in Port Alberni

“Does Kirby care?” B.C. First Nation’s group using geo-targeted ads in Houston, Texas for justice

The Heiltsuk Tribal Council has called out Kirby Corporation for the Nathan E. Stewart oil spill

Trudeau announces $79M investment for 118 more public transit buses across B.C.

Contributions from municipal to federal level to fund more buses in a bid to cut commutes

B.C. woman wins record $2.1 million on casino slot machine

‘That night was so surreal … I wasn’t able to sleep or eat for the first two days,’ she said

After B.C. dad’s death, Technical Safety BC wants changes to trampoline park rules

Jay Greenwood, 46, did ‘a series of acrobatic manoeuvres prior to a fall that caused serious injury and cardiac arrest’

Cars keyed on BC Ferries after alarms bother dog on board

Delta police arrested one passenger on suspicion of mischief

$900M settlement reached in class action on sexual misconduct in Canadian military

After facing criticism, the government moved to begin settlement proceedings in early 2018

Tax take stays ahead of increased B.C. government spending

Tax revenue $2.1 billion higher than budget in 2018-19

Most Read