Metro Vancouver’s business case to build a second garbage incinerator grossly overestimates electricity revenue and underestimates the project’s costs, according to a report paid for by one of the plan’s biggest critics.

It estimates the net costs could be $800 million to $1.3 billion higher than Metro has estimated over the 35-year life of the new waste-to-energy plant.

The analysis was conducted by consulting firm ICF International and commissioned by waste disposal firm Belkorp Environmental Services, which stands to lose business if a new incinerator is built.

Belkorp operates the Cache Creek landfill – which Metro aims to stop using – and has proposed to build a material recovery facility in Coquitlam that it says could sort more recyclables from what is otherwise garbage.

Metro has assumed BC Hydro will pay $100 per megawatt-hour for the power that would be generated over the full life of the project, but the ICF report warns BC Hydro might renegotiate a much lower rate in 15 years, after Metro pays off its capital investment.

If the power price drops at that point to $43 per megawatt-hour – which Metro now receives at its existing Burnaby incinerator – electricity revenues would shrink by $362 million, the report said.

“One of the really heroic assumptions is the price of electricity that they are going to receive from BC Hydro,” ICF report lead author Seth Hulkower told Coquitlam council Monday.

ICF’s estimate of the lifetime project costs are also 18 per cent higher than Metro’s and it also adds a 15 per cent contingency for operations and maintenance.

Its “downside scenario” estimate of a $1.3-billion cost overrun makes bleaker assumptions than Metro and assumes the regional district must sell electricity on the open market without any fixed price guarantee from BC Hydro.

Metro officials say their business case does not necessarily reflect what the final waste-to-energy project may be.

One project proponent – Lehigh Cement – proposes to retrofit its Delta cement plant to use garbage as fuel, replacing coal and tires it now burns.

“It doesn’t need to sell electricity at all,” Metro board chair Greg Moore said.

The cement plant option may also have considerably lower capital costs than the estimate of around $500 million for an all-new plant.

Other scenarios could see a new waste-to-energy plant located near a densifying urban area where steam could heat surrounding buildings in a district energy system, instead of being converted to electricity for sale.

“It’s not shocking that this report comes from the largest private landfill operator that wants to continue operating their business as a landfill,” Moore said.

Metro’s current plan calls for construction of a new waste-to-energy plant to take up to 370,000 tonnes per year of garbage, an amount it estimates will still require disposal if the region’s recycling rate climbs from 60 per cent to 70 per cent.

But the regional district is expected to re-evaluate its plans in light of the province’s rejection of Bylaw 280, which tried to ban the hauling of garbage out of Metro.

Belkorp vice-president Russ Black said he hopes more mayors and councils around the region push the Metro board to place a moratorium on the incinerator plan in light of the ICF findings.

Councils in Maple Ridge, Pitt Meadows, Coquitlam and Port Moody have previously supported a moratorium.

Black said it’s “completely false” to suggest Belkorp’s aim is to keep taking Metro garbage to its Cache Creek landfill by defeating the incinerator, pointing instead to its NextUse subsidiary’s plan to sort recyclables from garbage.

– with files from Gary McKenna

Just Posted

Sunshine Valley teens burning with promise

Possibly the youngest in B.C., Sunshine Valley trains 15- and 16-year-old firefighters

Figures reveal spike in highway traffic jams between Abbotsford and Langley

Nearly one in 20 westbound vehicles between Abbotsford and Langley clocked at under 60 km/h

Taser takedown in Chilliwack complex after incident gets violent

Male suspect became agitated under questioning and repeatedly punched an officer

Hang gliding video gives stunning view of Harrison and Fraser river confluence

Aerial view shows striking difference between two rivers as they meet

Young Chilliwack singer launches career with French classic

Deanne Ratzlaff performs as featured vocalist in La Vie en Rose in Chilliwack, London and Paris

Rich the Vegan scoots across Canada for the animals

Rich Adams is riding his push scooter across Canada to bring awareness to the dog meat trade in Asia

Canadian high school science courses behind on climate change, says UBC study

Researchers found performance on key areas varies by province and territory

UPDATE: One dead after house fire in rural Maple Ridge

Dewdney Trunk Road closed, traffic being re-routed

Six inducted into BC Hockey Hall of Fame

The 26th ceremony in Penticton welcomed powerful figures both from on and off the ice

Highway 1 closed near Revelstoke

No estimated time for opening

CRA program to help poor file taxes yields noticeable bump in people helped

Extra money allows volunteer-driven clinics to operate year-round

RCMP investigate two shootings in the Lower Mainland

Incidents happened in Surrey, with a victim being treated at Langley Memorial Hospital

Recall: Certain Pacific oysters may pose threat of paralytic shellfish poisoning

Consumers urged to either return affected packages or throw them out

Most Read