B.C. pulls plug on power projects

BC Hydro has cancelled or deferred four electricity purchase contracts with independent power producers, and the total may reach 20

Wind turbine components await construction at independent power project near Chetwynd in 2008. High construction costs stalled B.C.'s first commercial wind energy project

BC Hydro has cancelled or deferred four electricity purchase contracts with independent power producers, and the total may reach 20 by the time a review of projects is complete, Energy Minister Bill Bennett said Thursday.

Bennett said the review is part of a broader effort by BC Hydro to meet his instruction to “spend less money,” as he leads an effort to reduce costs across all government operations.

BC Hydro proposed the move, identifying the 20 project proponents that were not meeting their contract obligations due to financing, regulatory or other problems. That non-performance gives BC Hydro legal authority to delay or terminate contracts.

The utility has contracts with 81 operating projects, mostly run-of-river hydroelectric, and another 47 are under construction or seeking permits after receiving purchase contracts.

BC Hydro released its latest draft resource plan last week, which estimates the province has enough electricity supply to meet growing demand for the next 10 years. Bennett said he is skeptical about that forecast, with population growth and industrial demand from new mines and natural gas development in northern B.C., but it gives the utility some breathing room.

“I’m a real fan of the clean energy industry, but obviously we don’t want to be agreeing to buy more power than what we need,” Bennett said.

BC Hydro has been criticized in recent years for running up billions in deferred debt, as it completes major expansion and seismic upgrading of its network of dams. A new power line to northeast B.C. has run over budget, and the NDP opposition has accused the government of forcing BC Hydro to buy private power at inflated rates through contracts running as long as 40 years.

Bennett said he has asked for a detailed analysis of the cost of private power compared to new sources such as the proposed Site C dam on the Peace River or adding turbines to BC Hydro dams on the Columbia River.

B.C.’s Clean Energy Act requires BC Hydro to be self-sufficient in electricity by 2016, based on an average rainfall year to replenish its hydro dams. The requirement is to minimize the import of power generated by burning coal or natural gas.

Just Posted

Hope school board candidates talk SOGI, successes and rocky patches of past four years

Six candidates are vying for three Hope trustee positions up for grabs in an Oct. 20 election

VIDEO: This is what buying legal pot in B.C. looks like

Take a look inside B.C.’s first and only legal pot shop located in Kamloops

Cindy Young makes second run for top political job at the District of Hope

Young, in her run for mayor, is campaigning to attract business to Hope and keep local youth in the community

10 things still illegal in the new age of recreational cannabis

Pot is legal – but there are still a lot of rules, and breaking some could leave you in jail

One of Chilliwack’s oldest clubs, Toastmasters, hosts an open public speaking event this month

An open house will take place on Oct. 24 at the Mt. Cheam Lions Club Hall at 7:15 p.m.

Mellow opening to B.C.’s only legal pot shop

About five people lined up early for the opening of the BC Cannabis Store in Kamloops.

Jagmeet Singh says marijuana pardons are not enough

Trudeau government will streamline pardon process for Canadians convicted of simple possession of marijuana in the past

BC Ferries begins taking debit in two-month pilot project

Company is giving customers option to use Interac on two-month trial on select vessels

Caregivers banned from smoking, growing cannabis around children-in-care: MCFD

Ministry has limited cannabis use for caregivers, stating it may “pose a risk to children and youth.”

Cheaper strains sell out within minutes on online BC Cannabis Store

Province says new strains will become available in the coming months

Only 40% of B.C. car dealerships have electric cars available: report

Researchers found buyers frustrated at the lack of options

VIDEO: Millionaire Lottery returns to give back and win big

Since 1996, Millionaire Lottery has raised $52 million for the VGH+UBC Hospital Foundation

Test case challenges a politician’s right to block people from Twitter account

3 people say Watson infringed their constitutional right to freedom of expression by blocking them

Most Read