Buyers hope for court win in Lower Mainland condo case

An appeal has been scheduled for pre-sale buyers in the Murrayville House case.

Would-be buyers of condos in the beleaguered Murrayville House project are appealing a judge’s decision that saw their pre-sale contracts cancelled.

Fred West has been waiting two and a half years since he and his wife put down their payment for a condo in the project.

After numerous construction delays plagued the project, it was finally completed physically late last year. However, legal wrangles between the creditors, the pre-sale buyers, and the builder continue. The project is in receivership and remains empty as ownership is sorted out.

On April 4, pre-sale buyers were devastated by a ruling that their contracts had essentially expired, and mortgage lenders to the project took priority.

The pre-sale buyers would have right of first refusal to buy their units, but at current market prices.

That’s impossible for many of the owners, who put down their deposits before condo prices skyrocketed.

“We paid somewhere in the vicinity of $340,000, and it was going to be listed for $503,000,” West said of the condo he’d planned to buy.

Now a judge has sent the matter to the B.C. Court of Appeals. A three-judge panel will hear arguments by a group of 22 buyers, represented by Solimano Law, on June 12.

“One for the little guys,” said West.

He admitted the buyers have no idea what the appeals court judges will decide, but he was very satisfied they’ll get a hearing.

If the appeals court overturns the ruling and sides with the pre-sale buyers, it could set a legal precedent for similar real estate situations in B.C.

On April 4, Justice Shelley Fitzpatrick had ruled that mortgage holders had legal priority over pre-sale buyers.

Creditors who financed various mortgages are owed more than $51 million in principal and interest.

The lenders had opposed allowing the pre-sale buyers to fulfill their contracts. They argued for selling the units at market price so they could recoup more of the money they are owed.

An appraisal of the project showed that the units’ value was 46 per cent higher than contract prices.

There are 92 units in the building. Courts are still sorting out the ownership of many of the remaining units, which had even more complicated issues to resolve. Fitzpatrick described the situation as “chaos” at one point in her April 4 judgment.

The primary developer of the project, Mark Chandler, was ordered extradited to the United States earlier this year to face a fraud charge in California. He is currently appealing that ruling.

The RCMP has also confirmed it is investigating the situation around Murrayville House.

Just Posted

UPDATE: One dead, two in hospital after Highway 1 crash near Bridal Falls

Closure expected to last hours, while drivers are told to take detours

B.C. Ferries cancels Swartz Bay-Tsawwassen sailings over propulsion problem

11:00 ferry now good to go, but lines anticipated

‘It’s a very real and acute issue:’ agriculture expert on food insecurity in Hope

New food and agriculture plan presented to public Tuesday

27 years of supporting victims and survivors of crime and trauma

Marianne Brueckert with Victim Services says it is a gift to work with survivors of crime, tragedy

VIDEO: Othello Tunnels open for season

Domestic and foreign tourists already filling park trail

Wildfire sparked north of Merritt, estimated 8 hectares

BC Wildfire Service is responding to the fire near Chattaway Lake FSR 27 kilometres north of Merritt

Heavy police presence after reported shooting in Richmond

Reports say a man was hit while riding a motorcycle

B.C. to spend $181M to create 200 general practitioner jobs

Jobs will go to new medical school graduates

Federal leaders trade barbs about India trip at press gallery dinner

Justin Trudeau’s infamous trip to India earlier this year was the focus of many of the jabs

Most Read